As part of the 220 kW transmission line project in Běchovice, we’ve successfully completed two rounds of material acceptance. These involve four pylons—three brand-new structures and one existing tower, which will be upgraded with reinforcement and a 6-meter height extension.
The second acceptance, a Factory Acceptance Test (FAT), was successfully carried out on April 22, 2025, confirming that all delivered components meet the specified technical and quality requirements. The entire project is overseen by ČEPS, and we’re pleased to report that everything is progressing according to plan.